Bronx Based Special Education School

Project Overview: Bronx Based Special Education School

This School had outdated and discontinued T-12 light fixtures throughout the school. With the need to upgrade the lighting without major disturbance to the building infrastructure they did a lighting retrofit project to reduce the electrical and HVAC load in the building.

INF associates worked closely with property management to design and implement this LED lighting project, which has received a substantial custom rebate awarded by the Con Edison Commercial & Industrial Rebate program, coming in at $28,650.00

Interesting Fact

The customer expects to save nearly $353,639.00 over the lifetime of the product
Project Overview:

Total Project Costs: $146,306.00
KWH Saved Pear Year:392,932
KW Saved Per Year: 43.6
Dollars Saved Per Year: $39,846.00
Con Edison Incentive: $28,840.00
Cost to Customer: $117,466.00
Payback Period: 22 Months
ROI: 54%